KENWICK SCHOOL HYDROTHERAPY POOL TILE REPLACEMENT PROJECT 

Programmed Facility Management

December ’22 – January ’23 (School Holiday Period)

Project Cost: $0.15m

The renovation & upgrade of the Hydrotherapy Pool at Kenwick School for Programmed Facility Management was fully completed during the School Christmas Holiday period of December 2022. We worked closely with our sister company to ensure tiling of pool was to the highest of standards.

 

043e42e0-49cf-4500-aa2c-1a43051a09e6
0c940018-94e0-4294-905e-8ab522f4a09c
774c4045-9da5-49b8-84ba-65669c5a4114
0c940018-94e0-4294-905e-8ab522f4a09c (1)
57f849f5-603b-4d1b-a28d-0c379ff08cd3
a9f2ebb7-6d93-433a-8155-754f04ff26a7
afad7831-b423-4e67-a461-7081b606ddda
7d0a5f4e-efa4-485f-9b2b-c1c72fa6300f
f6873c80-2464-4324-992c-015fcae66554
c19abfe1-ba19-4c61-aa6d-6ea572824b51
ea6a8ef3-6dcf-4d61-bbc8-b2cc03c83512
DESCRIPTION OF WORKS
  • Demolition (In-House) of existing tiled surface and render (plaster) back to concrete structure including minor concrete repairs.

  • Application of primer & waterproof membrane to all tiled areas including hob prior to install of new render (plaster). 

  • Replace tiles to whole of pool including internal, ramp, entry to ramp and hob of pool as required under AS3979:2006 for Hydrotherapy pools and AS3958 Series including full Epoxy Grout (Mapei) System.

  • Upgrade of floor returns, wall inlets, depth markers, and skimmer box dress rings and lids. 

  • Polishing of existing Stainless Steel handrails including modifications and equipotential bonding works in accordance with the requirements of AS/NZS 3000 and Department of Education requirements. 